Archives

Norwich Victoria Sidings – Enabling Works

Client Name
Greater Anglia Abellio

Project Name
Norwich Victoria Sidings Enabling Works  

Sector
Permanent Way & Devegetation

DURATION
Dec 2018 – March 2019

LOCATION
Norwich

Please contact : 01707 927 400

email : info@prorailservices.co.uk

Norwich Victoria Sidings – Enabling Works

THE CHALLENGE

This was an enabling works project comprising of:

  • Vegetation Clearance
  • Arborist Works
  • Track Removal
  • Formation Grading Works
  • Survey, Design & Assurance Works for a new access ramp installation

These works were required to be executed ahead of a Main Contract to install new sidings with associated O.L.E and Permanent Way assets.  We were appointed as Principal Contractor to deliver this Design & Build Project with a very tight timescale of 12 weeks to hand over to the major works team.

The enabling works could not be allowed to induce any negative impact to the adjacent Norwich to London Mainline.  We therefore devised an access strategy plan and ALO plan to ensure our works did not impact on train services.

THE SOLUTION

Pro Rail Services was required to execute a Track dilapidation survey in accordance with the Network Rail AMP process, in advance of the site clearance works.

A topographical survey and a detailed design submission with assurance documentation was required to allow the production of a new design for a temporary access ramp down into the proposed new sidings.

We then set up a separated temporary fence line to separate the worksite so that all works could be executed on mid-week day shifts.

THE IMPLEMENTATION

We executed the site compound mobilisation ahead of the main works so that we could install the site offices to control the worksite.

Major devegetation and arborist work – over 5200m2 of devegetation, root removal and application of herbicide plus tree felling to circa 25 trees.

Regrading to the cutting adjacent to the redundant Road 1 for circa 180m x 4m.

Burning of rails in to 5m lengths on 4 redundant roads, each 260m long and stockpiling at the loading bay end of the site.

Removal of over 1500 redundant timber sleepers and stockpiling for off-site disposal to a waste transfer facility.

Regrading to the underside of the old timber sleeper position.

Design, full Railway Assurance and installation of a temporary access ramp to facilitate heavy plant access to site for the follow on new P-Way and OLE installation main works project.

THE RESULTS

Programme:
The site works was executed over a 8 week period from early January to the end of February 2019 and beat the original site construction programme by 4 weeks.

HSEQ Responsibilities:
Pro Rail Services Ltd was the Principal Contractor on this Project and worked collaboratively with GA to ensure that this project was delivered efficiently, on time and without any major accidents or injuries. This was achieved by ensuring we continue to use our behavioural safety approach to all projects, thorough and regular safety briefings and always ensuring that only competent persons are actually executing the required task.

Budget:
The Project was delivered to its target budget.

Stakeholder Management:
Pro Rail Services as Principal Contractor, managed all stakeholder interfaces with: Greater Anglia Abellio, Network Rail (Anglia Route), Designer, adjacent business’s to the worksite, site team and the supply chain to ensure that we all worked together collaboratively to achieve the successful outcomes listed above.

The enabling works were completed ahead of programme thus ensuring that the worksite was handed over on time to the main works contractor.

Please contact : 01707 927 400

email : info@prorailservices.co.uk

Walkways, Fencing Repairs and New Gates

Client Name
Network Rail Tier 1 Contractor

Project Name
Walkways, Fencing Repairs, New Gates and Steps Project 

Sector
Safe Access and Egress Points

DURATION
6 Months

LOCATION
South East Route

Please contact : 01707 927 400

email : info@prorailservices.co.uk

Walkways, Fencing Repairs and New Gates

THE CHALLENGE

Network Rail South East Route were required to achieve to deliver a number of minor civils projects between October 2018 and end of March 2019.

A number of these projects required initial site scoping surveys and non- complex designs to be executed ahead of the implementation stage.

A key challenge to address was the sheer volume of works to be executed prior to the close out of the financial year.

Mobilisation and target execution dates were very tight.

THE SOLUTION

We decided to use our Horsham Yard as a control centre and materials distribution point for the various gangs to co-ordinate all plant and material requirements to be issued for each individual site.

Procurement schedules were generated to ensure that all project requirements were controlled and all material and plant requirements would match the required specification for the works.

In addition to submitting all HSEQ documentation, we ensured that progress reports including before and after photos were issued to the client on a weekly basis.

Our Senior Management was extensively involved with ensuring all works was safely and efficiently delivered to programme.

THE IMPLEMENTATION

Our customer (a NR Tier 1 contractor), issued us with a schedule of sites with various types of minor civils works to be delivered, such as: New walkways, lineside fencing, vegetation management works, installation of new RRAP’s, new access points and new signage at said access points. There were over 50 sites requiring works to be executed on.

We developed a master programme schedule to allow for: initial site visits, generation of detailed scoping documents, programme for each worksite and subsequent quotation to be submitted to NR through our Tier 1 client. The master programme allowed for the generation and submission of Survey reports and fabrication drawings, procurement schedules, WPP’s, Task Briefs and site files including I&T Plans.

THE RESULTS

Between October 2018 and March 31st 2019, Pro Rail Services delivered:
• 54 Access Points to a variety of Embankments & Cuttings
• 321 metres of new tanilised timber edge walkways
• 30 new gates were installed • 54 number of access point signage erected
• 400 No of lineside sub-station buildings surveyed to develop scopes for follow on repairs
• Seven new timber RRAPs installed

All works delivered to specification, programme and with a project AFR of 0.00.

Please contact : 01707 927 400

email : info@prorailservices.co.uk

Walton on Thames Track Drainage Renewal Project

Client Name
Network Rail

Project Name
Walton on Thames Track Drainage Renewal Project

Sector
Railway Drainage

PROJECT VALUE
£55,000

DURATION
27 hours 

LOCATION
Walton-on-Thames, SW London 

Please contact : 01707 927 400

email : info@prorailservices.co.uk

Walton on Thames Track Drainage Renewal Project

THE CUSTOMER
Pro Rail Services Ltd. is a Railway civil engineering contractor who execute maintenance contracts on Network Rail infrastructure. This project took place on the Wessex Route.

THE CHALLENGE
The track drainage system in the area had a history of partial collapses, which lead to numerous track flooding events.

Network Rail was keen for this to be addressed as part of its planned maintenance programme. Pro Rail Services Ltd. was commissioned to replace track drainage, by installing 145 metres of new track drainage to cover both the Up and Down CESS during a 27-hour weekend daytime possession.

Timescales were tight. The project was tendered five weeks before possession. Pro Rail Services Ltd. was awarded the contract with three weeks to plan the works and mobilise its teams.

THE SOLUTION
The Pro Rail Services Ltd. planning team quickly put together a project plan that would ensure the works could be completed safely and effectively within the 27-hour limit.

The track drainage renewal teams consisted of four site managers, six engineers and 55 skilled rail maintenance operatives working across both locations.

Four road rail excavators, with trained RRV operators, and a team of crane and machine controllers were also brought in.

Materials, including 600 tonnes of ballast, were transported to the site by engineering trains.

THE IMPLEMENTATION
Over the 27-hour possession, the Pro Rail Services Ltd. teams installed 145 metres of new track drainage pipe at Walton-on-Thames Station.

First, the old pipework had to be excavated and removed. The new pipework was 450-millimetre diameter half-perforated plastic (HDPE). Ballast was laid within trench liner membrane to prevent root ingress.

Five new catchpits, made from glass-reinforced plastic (GRP) were also installed. The new track drainage lines were then jetted clean and surveyed by one of Pro Rail Services Ltd.’s CCTV camera teams, to show the pipework was fit-for-purpose and fully-operational.

The amount of new track drainage pipes

THE RESULTS

145m of new track drainage installed within the 27-hour possession

All works carried out safely, with no incidents reported, precisely to Network Rail’s specification

Potential risk to passenger services from track flooding greatly reduced by installation of an optimum track drainage solution

Network Rail is fully-appraised of scope of phase 2 works to replace remaining track drainage at the Station

Please contact : 01707 226 501

email : info@prorailservices.co.uk

Teynham – Level Crossing Renewal

Client Name
Network Rail

Project Name
Teynham – Level Crossing Renewal 

Sector
Railway Level Crossing 

PROJECT VALUE
£49,000

DURATION
27 hours

LOCATION
Teynham, Kent 

Please contact : 01707 927 400

email : info@prorailservices.co.uk

Teynham – Level Crossing Renewal

THE CUSTOMER
Pro Rail Services Ltd. is a Railway civil engineering contractor who execute maintenance contracts on Network Rail infrastructure. This project took place on the South East Route.

THE CHALLENGE
Pro Rail Services was commissioned to replace a level crossing STRAIL system on the Medway Valley Line in North Kent.

This was a complex project owing to the need to repair the drainage under the crossing and the presence of buried services connecting nearby residences.

Health and safety considerations included restrictive working on the level crossing, and manual handling of heavy materials and equipment.

THE SOLUTION
A topographical survey was carried out. Data was used to create a design approved by Network Rail South East. Work was carried out in partnership with the rail crossing system manufacturer, STRAIL. All work was undertaken under a pre-planned 27-hour possession.

Extra care was needed to ensure there was no damage to the buried services.

As requested by the client, steel beams were used to support the STRAIL mats.

While replacing the mats, spot repairs would be made on the drainage underneath.

THE IMPLEMENTATION
Personnel deployed per 12-hour shift were:
• 6 skilled rail operatives
• 1 track handback engineer
• 1 COSS
• 1 Site Manager

The existing steel beams were reused and were removed and reinstalled using a 3-tonne excavator.

All arisings were put in 1-tonne bags and removed from site using a lorry with a truckmounted crane.

More than 50 STRAIL mats were installed.

Finally, road markings were re-painted prior to the crossing re-opening.

THE RESULTS
• The project was completed ahead of schedule and on budget, to Network Rail’s specification

• In addition, trespass guards were also repaired

• All work was carried out safely, with no incidents reported. No services we struck.

Please contact : 01707 226 501

email : info@prorailservices.co.uk

St Stephens – Level Crossing Renewal

Client Name
Network Rail

Project Name
St Stephens – Level Crossing Renewal 

Sector
Railway Level Crossing 

PROJECT VALUE
£47,000

DURATION
27 hours

LOCATION
St Stephens, Canterbury 

Please contact : 01707 927 400

email : info@prorailservices.co.uk

St Stephens – Level Crossing Renewal

THE CUSTOMER
Pro Rail Services Ltd. is a Railway civil engineering contractor who execute maintenance contracts on Network Rail infrastructure. This project took place on the South East Route.

THE CHALLENGE
Pro Rail Services was commissioned to replace a level crossing STRAIL system on the Medway Valley Line in North Kent.

The level crossing was close to a large industrial site and had significant HGV traffic. in a poor condition, leading to numerous vehicles becoming stuck, causing significant safety hazards. The drainage running under the crossing was also in disrepair and needed to be improved.

Health and safety considerations included restrictive working on the level crossing, and manual handling of heavy materials and equipment. The concrete beams, alone, weighed 0.4 tonnes per metre.

THE SOLUTION
A topographical survey was carried out. Data was used to create a design approved by Network Rail South East. Work was carried out in partnership with the rail crossing system manufacturer, STRAIL. All work was undertaken under a pre-planned 27-hour possession.

Road closures were needed due to the location of the works. To minimise inconvenience to the travelling public, the project had to be completed in just 27 hours.

With the high HGV traffic, a pontiSTRAIL system was used throughout due to its capacity for heavy loads. To facilitate this system, it was necessary to install concrete beams in the sixfoot and cess.

THE IMPLEMENTATION
Personnel deployed per 12-hour shift were:
• 6 skilled rail operatives
• 1 track handback engineer
• 1 COSS
• 1 Site Manager

This work included removing the existing steel beams using a 3-tonne excavator and installing the new concrete beams.

All arisings were put in 1-tonne bags and removed from site using a lorry with a truckmounted crane.

More than 50 pontiSTRAIL mats and trays were installed, along with concrete beams weighing a total of 12 tonnes.

Finally, road markings were re-painted prior to the crossing re-opening.

THE RESULTS
• The project was completed ahead of schedule and on budget, to Network Rail’s specification

• In addition, trespass guards were also repaired

• All work was carried out safely, with no incidents reported.

Please contact : 01707 226 501

email : info@prorailservices.co.uk

Snodland – Level Crossing Renewal

Client Name
Network Rail

Project Name
Snodland – Level Crossing Renewal 

Sector
Railway Level Crossing 

PROJECT VALUE
£54,000

DURATION
27 hours

LOCATION
Snodland

Please contact : 01707 927 400

email : info@prorailservices.co.uk

Snodland – Level Crossing Renewal

THE CUSTOMER
Pro Rail Services Ltd. is a Railway civil engineering contractor who execute maintenance contracts on Network Rail infrastructure. This project took place on the South East Route.

THE CHALLENGE
Pro Rail Services was commissioned to replace a level crossing STRAIL system on the Medway Valley Line in North Kent. To facilitate the new STRAIL system it was necessary to install concrete beams in the six-foot.

Due to the location of the works, road closures were needed. To minimise inconvenience to the travelling public, the project had to be completed in just 27 hours.

Health and safety considerations included restrictive working on the level crossing, and manual handling of heavy materials and equipment. The concrete beams, alone, weighed 0.4 tonnes per metre.

THE SOLUTION
A topographical survey was carried out. Data was used to create a design approved by Network Rail South East. Work was carried out in partnership with the rail crossing system manufacturer, STRAIL. All work was undertaken under a pre-planned 27-hour possession.

THE IMPLEMENTATION
Personnel deployed per 12-hour shift were:
• 6 skilled rail operatives
• 1 track handback engineer
• 1 COSS
• 1 Site Manager

This work included removing the existing steel beams using a 3-tonne excavator and installing the new concrete beams.

All arisings were put in 1-tonne bags and removed from site using a lorry with a truckmounted crane.

More than 50 STRAIL matts and pontiSTRAIL trays were installed, along with concrete beams weighing a total of 12 tonnes. Finally, road markings were re-painted prior to the crossing re-opening.

THE RESULTS
• The project was completed ahead of schedule and on budget, to Network Rail’s specification

• In addition, trespass guards were also repaired

• All work was carried out safely, with no incidents reported.

Please contact : 01707 226 501

email : info@prorailservices.co.uk

Sidcup & Crayford Track Drainage Renewal Project

Client Name
Network Rail

Project Name
Sidcup & Crayford Track Drainage Renewal Project

Sector
Railway Drainage

PROJECT VALUE
£55,000

DURATION
27 hours

LOCATION
Bexley, SE London

Please contact : 01707 927 400

email : info@prorailservices.co.uk

Sidcup & Crayford Track Drainage Renewal Project

THE CUSTOMER
Pro Rail Services Ltd. is a Railway civil engineering contractor who execute maintenance contracts on Network Rail and TfL infrastructure. This project took place on the South East Route.

THE CHALLENGE
Sidcup and Crayford railway stations are both on the HDR Line (Hither Green Junction to Rochester) in South East London. Both, also, had been identified as pinch points in the track drainage system, where there was heightened risk of flooding, which could affect passenger services.

Network Rail was keen for this to be addressed as part of its planned maintenance programme. Pro Rail Services Ltd. via UKDN Waterflow was commissioned to replace track drainage at both stations, during a 12-hour weekend daytime possession.

Timescales were tight. The project was tendered five weeks before possession. Pro Rail Services Ltd. was retained with three weeks to plan the works and mobilise its delivery teams.

THE SOLUTION
The Pro Rail Services Ltd. planning team quickly put together a project plan that would ensure the works could be completed safely and effectively at both stations, which are two miles apart, within the 12-hour limit.

The track drainage renewal teams consisted of four site managers, six engineers and 75 skilled rail maintenance operatives working across both locations.

Four road rail excavators, with trained RRV operators, and a team of crane and machine controllers were also brought in.

Materials, including 300 tonnes of ballast, were transported to the site by engineering trains.

THE IMPLEMENTATION
Over the 27-hour possession, the Pro Rail Services Ltd. teams installed 60 metres of new track drainage pipe at Sidcup station, and 40 metres at Crayford Station.

First, the old pipework had to be excavated and removed. The new pipework was 225-millimetre diameter half-perforated plastic (HDPE). Ballast was laid within trench liner membrane to prevent root ingress.

At both stations, three new catchpits, made from glass-reinforced plastic (GRP) were also installed. The new track drainage lines were then jetted clean and surveyed by one of Pro Rail Services Ltd.’s CCTV camera teams, to show the pipework was fit-for-purpose and fullyoperational.

THE RESULTS
100m of new track drainage installed at two stations within the 27-hour possession time

All works carried out safely, with no incidents reported, precisely to Network Rail’s specification

Ability of Asian longhorn beetle to spread greatly curtailed

Potential risk to passenger services from track flooding greatly reduced by installation of an optimum track drainage solution

Network Rail is fully-appraised of scope of phase 2 works to replace remaining track drainage at Crayford Station.

Please contact : 01403 822701

email : haulage@prorailservices.co.uk

Pens Parsonage – Culvert Repairs

Client Name
Geoffrey Osborne for Network Rail Wessex Route

Project Name
Pens Parsonage – Culvert Repairs

Sector
Railway Drainage

PROJECT VALUE
£48,000

DURATION
10 mid-week shits

LOCATION
Pen Parsonage, Somerset

Please contact : 01707 927 400

email : info@prorailservices.co.uk

Pens Parsonage – Culvert Repairs

THE CUSTOMER
Pro Rail Services Ltd. is a Railway civil engineering contractor who execute maintenance contracts on Network Rail infrastructure. This project took place on the Wessex Route for Geoffrey Osborne Ltd.
THE CHALLENGE
The drainage system in the area had a history of blockages, which lead to numerous flooding events on neighboring properties.

Network Rail was keen for this to be addressed as part of its planned maintenance programme. Pro Rail Services Ltd. was commissioned to execute tree removal, de-vegetation, culvert masonry repairs, de-silting of the culvert and patch lining installation.

Timescales were tight. The project was tendered five weeks before commencement. Pro Rail Services Ltd. was awarded the contract with three weeks to plan the works and mobilise its teams.

THE SOLUTION
The Pro Rail Services Ltd. planning team quickly put together a project plan that would ensure the works could be completed safely and effectively at both culvert ingress and egress portals.

The team consisted of one site manager and five skilled rail maintenance operatives.

Plant included vans, compressors, chainsaws, brush cutters, jetting and drainage CCTV equipment

Materials, including cement and masonry, were transported to the site by highway based vehicles.

THE IMPLEMENTATION
Over 10 mid-week shifts, heavy vegetation and trees were removed by Lantra and NPTC competent operatives.

Once this phase was complete, the process of removing over 25 tonnes of silt commenced in order to enhance the space in the culvert to facilitate repair works.

Following the completion of the tree felling, devegetation, damming of the culvert and removal of channel silt, the required masonry replacement and joint repairs were then executed in accordance to programme and specification.

All operatives involved with the culvert repair works were competent confined space operatives using equipment calibrated and checked prior to execution on site.

THE RESULTS
Potential risks of flooding to neighbouring properties greatly reduced by the removal of silt and vegetation from the culvert and drainage channel

Unsafe tree carefully removed by competent operatives

Further deterioration of the culvert prevented by masonry repairs

Culvert successfully de-silted, preventing potential of future flooding events

Safe access to the culvert created to ease future maintenance or inspection activities

Please contact : 01403 822701

email : haulage@prorailservices.co.uk

SE Route Ditch and Culvert Clearance

Client Name
Network Rail

Project Name
SE Route Ditch and Culvert Clearance

Sector
Railway Drainage

PROJECT VALUE
£725,000

DURATION
18 months

LOCATION
Kent and Sussex

Please contact : 01707 927 400

email : info@prorailservices.co.uk

SE Route Ditch and Culvert Clearance

THE CUSTOMER
Pro Rail Services Ltd. is a Railway civil engineering contractor who execute maintenance contracts on Network Rail infrastructure. This project took place on Network Rail’s South East Route of the network.

THE CHALLENGE
Pro Rail Services Ltd. was commissioned to carry out three large packages of work to extensively improve trackside drainage ditches and rail culverts at multiple locations across its operational region.

There were varying challenges at each site. A key issue was access, as many drainage assets are located adjacent to farmland. Extensive liaison was needed with landowners. There were three categories of work:
1. Clearance of railway drainage ditches
2. Cleaning and surveying of railway culverts
3. Cleaning and surveying of track drainage

The programme involved many locations highlighted by the Office of Rail Regulation (ORR) as having embankment and flooding issues.

THE SOLUTION
All the sites were surveyed before work was carried out. Detailed project safety, environmental and logistical plans were drawn up for each package. Work was scheduled with the agreement of Network Rail Works Delivery South East Route.

Teams of specialist de-vegetation and access contractors with the right qualifications, skills and experience were put together. This included arborists, excavation crews, plant operators and drainage survey operatives.

SSOWP risk assessments and work package plans and task briefs were prepared for all projects, and all three projects were F10 notifiable.

THE IMPLEMENTATION
Work began in mid-August 2016 and is scheduled to finish at the end of 2017.
All sites have been visited and scoped. All work to-date has been carried out with a mix of daytime working and possessions with progress monitored through weekly meetings with Network Rail.
Clearance of railway drainage ditches
• Resources deployed have been a fiveperson de-vegetation team, supported by excavator and dumper crews, plus an array of safety critical resources.
Cleaning and surveying of railway culverts
• Culverts and track drainage lines are identified and their locations recorded.
• Where necessary, de-vegetation takes place.
• Culverts are dewatered through overpumping.
• Cleaning is carried out using water jetting.
• Asset condition surveys are carried out.
• Resources deployed include 10 operatives per site, a jet vac tanker, water tanker, offroad tracked Porta Reel, a CCTV camera survey team, and a 6-inch water pump.

THE RESULTS
• Vegetation and trees removed along 7,650 metres of trackside drainage ditch. Where necessary, ditches have been reprofiled.
• 38 under-track culverts have been cleaned and surveyed. In some cases, recommendations have been made to line the culverts or rebuild headwalls.
• Approximately 13,500m of track drainage completed across two routes (KJE2/3 – 7,500m, VTB3 – 6,000m) was maintained. Where necessary, recommendations have been made to carry out repairs to resolve a range of problems, including pipe cracking and collapses.

Please contact : 01707 226 501

email : info@prorailservices.co.uk

Belvedere Track Drainage Installation

Client Name
Network Rail

Project Name
Belvedere Track Drainage Installation

Sector
Railway Drainage

PROJECT VALUE
£160,000

DURATION
48 hours

LOCATION
Belvedere, Kent

Please contact : 01707 927 400

email : info@prorailservices.co.uk

Belvedere Track Drainage Installation

THE CUSTOMER
Pro Rail Services Ltd. is a Railway civil engineering contractor who execute maintenance contracts on Network Rail infrastructure. This project took place on Network Rail’s South East Route of the network.

THE CHALLENGE
Rail services through Belvedere Railway Station in the London Borough of Bexley were being compromised by poor track drainage causing wet beds. This resulted in temporary speed restrictions having to be put in place, adversely affected the reliability of passenger services.

The main cause of the problem was the lack of track drainable assets at the station.

THE SOLUTION
Pro Rail Services Ltd. was commissioned to install 170 metres of new track drainage. This was made up of semi-perforated high density polyethylene (HDPE) pipe (internal diameter: 225mm), linked via 6 glassreinforced plastic (GRP) catchpits.

Initially, the track drainage was designed to outfall into an existing culvert. However, it was identified that project costs could be reduced by moving the outfall to a ditch nearer to the station. The change was approved 10 days before the implementation date. However, Pro Rail Services Ltd. still had time to introduce an innovation. In what is thought to be a first for track drainage, the pipe outfall was established with a GRP headwall, instead of a concrete one.

GRP headwall – key benefits:
• Improved safety, through a reduction in manual handling risks. The GRP headwall weighed just 50kg
• Faster installation, due to the reduction in weight, more compact design and no need for specialist lifting equipment
• Reduced cost, due to no need for hire of lifting equipment and easier transportation.

THE IMPLEMENTATION
A railway drainage systems manufacturer, Aqua, was commissioned to design and supply the GRP headwall.

The track drainage system was installed during a 52-hour possession between 7-10 April 2017. Work was carried out in 12-hour shifts, with 50 track drainage personnel working on each shift.

4x road-rail vehicles (RRVs: 2x PC118, 2x PC138), 2x 5-tonne excavators and 2x trailer units were used to carry materials and equipment to and from the worksite.

At one point, work had to be suspended for three hours, and all equipment and materials were demobilised and transported to a depot three miles away, to allow two tamper trains to travel through the station.

THE RESULTS
Early indications are that the wet beds that were previously identified have been removed.

A new method for creating a track drainage outfall, using a GRP headwall, has been implemented. This technique can now be used again elsewhere, generating the benefits described above.

The track drainage was installed according to the programme and on budget. The GRP headwall was installed successfully and performed in line with specification. No incidents or accidents were reported.

Please contact : 01707 226 501

email : info@prorailservices.co.uk